Project planning and evaluation
Table of Contents
- Introduction
- Project lifecycle
- Where are you in the project lifecycle?
- Phase 1 - Needs assessment
- Phase 2 - Project planning
- Phase 3 - Implementation
- How to develop your project plan
- Evaluation planning
- How to develop your evaluation plan
- Terminology
- Appendix 1 - Sample project plan
- Appendix 2 - Sample evaluation plan
Introduction
This guidance document aims to help you build a viable project plan for a crime prevention project.
Projects need to demonstrate clear goals, objectives and viability - with measurable outcomes and indicators. This document provides you with the preliminary planning framework to help you build such a project.
There are essentially three phases in a project lifecycle:
- Phase 1 - Needs assessment
- Phase 2 - Project planning
- Phase 3 - Implementation
While not a separate phase, evaluation (which includes ongoing, mid-term, and final evaluation) is an essential part of the cycle, occurs throughout the life of the project, and informs all phases.
Project lifecycle
Where are you in the project life cycle?
You will first need to determine the phase for which you will be seeking funds.
Phase 1: Needs assessment
Your group knows there are some crime problems/issues in the community, but you do not know how big the problems are, whom they affect or what should be done about them. This is the very beginning of the project lifecycle, Needs Assessment, and it could be the focus of a project.
Phase 2: Project planning
Your community has already identified the specific crime or victimization problem/needs in your community and now wants to plan specific crime prevention activities to address those issues. This is the second phase of the project lifecycle, Project planning, and it could be the focus of a project.
Phase 3: Implementation
Your group knows the problems/issues in your community, you have consulted the community and developed a project plan with specific crime prevention activities to address those problems/issues and you are ready to start the project. This is the third phase of the project lifecycle, Implementation, and it could be the focus of a project.
Phase 1 - Needs assessment
This part of the project lifecycle focuses on the community and identifies the specific crime-prevention issue, problem or need to be addressed. It aims to also identify the risk factors that help to explain why a problem exists and the protective factors that can contribute to the solution. (for definitions and examples, see the Risk and Protective Factors fact sheet, which can be found in the Applicants Guide.)
The following are questions that you will need to answer in order to build a plan and submit a project proposal for this phase. By answering the questions you will give structure to your project objectives and determine the necessary inputs and activities.
On what specific crime or victimization issue in your community will this project focus?
- How was the issue first identified? (Who noticed it? When? Why?)
- How do you know there is a need to develop a project to respond to this issue?
- What are some of the risk factors and protective factors linked to this issue?
- Which of these risk factors do you think you can change?
- Upon which of these protective factors do you think you can build?
- Who can you contact or where can you go to get information, feedback or suggestions to develop project ideas or activities?
Refer to Appendix 1 - Sample project plan for an example that includes a needs assessment phase.
Phase 2 - Project planning
This part of the project lifecycle builds on what was discovered in the first phase. It focuses on what your crime prevention project is actually going to do and how it will address the problem/needs identified in your community. You will need to answer the following questions before assembling the comprehensive project plan:
- Who will be the focus of the project (e.g. youth, women)?
- What is the overall goal of your crime prevention project ? What do you want to change?
- What are possible solutions to address the identified issue, need or problem in your community?
- Which solutions seem most realistic and suitable?
- What are the objectives of your crime prevention project? What type of activities would achieve your objectives? What are the different steps you will have to take?
- What products, goods or services do you expect to produce or deliver as part of your project (e.g. training sessions, manuals, pamphlets, curriculum, CD/DVD, video, database, website, reports, etc.)?
- What will be the short-term results or outcomes of your activities? These will in turn contribute to achieving your objectives and overall goal(s).
After you identify what your crime prevention project could do, make a plan to put it into action:
- When will you do what? (Draw up a schedule of activities with start and end dates for each.)
- Where will the activities take place?
- Who will participate in each activity? How many? How will you get people to participate?
- What resources will you need (e.g. staff, volunteers, work space, photocopying, advertising, supplies, phone, computer equipment, transportation, etc.)? (These resources will need to be listed in your budget; see the Budget guidance document which can be found in the Applicants Guide.)
- How will you get these resources (e.g. donations of products or services, financial support)?
- How will you get the community (and in particular, members of the priority group) involved in developing the project?
- How will you find partners? Who will be your partners? What will they contribute (e.g., money, materials, volunteers, training, etc.)?
- How will you share information about your project? With whom? How will the community learn about it?
- What is your evaluation plan? How will you monitor the progress of your project? How will you collect information? (See explanation under Evaluation later)
- What are some possible challenges you might face in doing your project? How will you deal with them?
Refer to Appendix 1 - Sample project plan for an example of the project planning phase of a project.
Phase 3 - Implementation
This is the phase of the project lifecycle where your crime prevention project comes to life.
How will you start the project?
- Do you have a clear project work plan (see Phase 2 - Project planning)?
- Is everything accounted for in your budget?
- Do you have things in place to carry out, monitor and evaluate your project?
Refer to Appendix 1 - Sample project plan for an example of the Implementation phase of a project.
How to develop your project plan
Using your answers to the questions in the first part of this guidance document, you are now ready to build your project plan. The steps described demonstrate how you would go about developing your project plan.
- Identify your project goaland who you intend to serve.
- Identify the objectives that will lead to your goal.
- Establish what the components of your project will be - that is, your broad strategies or service areas.
- Describe the project inputs. Who and what will be required to operate your project?
- For each component, describe your activities. Who will do what, and when?
- Identify the outputs of your activities. How many participants do you expect? What (and sometimes, how many) tools, materials, or events will be produced?
- Identify the outcomes linked to these activities. Remember that outcomes represent changes you hope to see result from your activities; they are not just the delivery of the activities themselves. You will want to mention the short-term and intermediate outcomes of your activities, making sure that these in turn link to your overall goal(s).
Refer to Appendix 1 - Sample project plan for an example and Terminology for definitions.
More about objectives and outcomes
When you identify your own objectives and outcomes, be sure they are "SMART":
- Specific
- Measurable
- Achievable
- Relevant (and realistic)
- Trackable
Objectives and outcomes should be described with action words that indicate the direction of change. Words such as "increase", "improve" or "reduce" are good examples. Saying that a project objective is "to provide recreational opportunities" does not tell us anything about the purpose of those recreational activities or the changes they are expected to bring about. Programs or projects are developed to make change. They are not developed simply for the sake of delivering products or services alone. Saying that these recreational opportunities are going to increase teamwork and leadership skills or reduce vandalism in the after-school hours makes them into SMART objectives.
Evaluation planning
Evaluation planning comes down to two questions:
- What are the desired outcomes of your project?
- How will you measure them?
It is about building benchmarks and accountability into your plan, and using them to evaluate the plan as you go and after the project is finished. It gives your project a more strategic structure, provides evidence for your results and, importantly, contributes to the knowledge base about effective crime prevention.
Valid and reliable measurement tools
Valid measurement tools provide information that is a good reflection of what they are trying to measure. For example, if you wanted to measure the extent to which people were victims of a certain type of crime, you might want to look at more than just the number of reports to police since we know that many crimes are unreported.
Reliable instruments provide information that is likely to be consistent over time. It will not be affected by small changes in such things as the mood of people who respond to a survey or other circumstances unique to the day on which they complete the survey.
Quality and consistency
Quality evaluations also use consistent data collection procedures. For example, interview questions should be asked to all participants in the same way, and interviewees should be careful to record the same information at every session.
Where possible, collect data before and after a project. When data is collected only at the end of the project, you can't tell whether there was actually any change that occurred.
Good evaluations require resources - that is, time and money. Some evaluation-related activities may be carried out by project staff (for example, questionnaires can be administered by a project coordinator), research assistants (for example, students may compile and analyse data) or by people with special expertise (for example, an evaluation consultant might draft your questionnaire).
Be realistic when establishing the outcomes you choose to measure
Your project goal might be to reduce the number of a certain type of crime in your community. This may require the modification of behaviour in a community that takes place over five to ten years to achieve any reduction. To measure those long-term trends may not be realistic. In this case, you should focus on some short- and medium-term outcomes.
How to develop your evaluation plan
The steps described demonstrate how you would go about developing your evaluation plan.
- Determine what information you will need to collect:
- To see how your project is doing day to day (on-going monitoring)
- To see if you are on track to achieve your intended results, if you are on time and if you are using resources as planned mid-way through your project (mid-term evaluation), so that you may make adjustments as needed
- To see if the overall changes you were trying to achieve actually happened by the end of the project (final evaluation) and identify what you learned.
- Determine your information sources/data collection methods. Sources of information may include project staff, other agencies, participants and their families, members of the public and the media. Information may be collected via a variety of methods, including:
- Project records such as project activity log/daily journal: A book where you write down what happens each day. It is a useful source to document many of your indicators and will be helpful to you when writing the final project report.
- Number and type of documents produced during the project (tools, flyers, advertisements, media coverage of your event/project, curriculum, etc)
- Information collected about your participants related to the project (number attending sessions, information about who they are - age, gender, education, background, culture, etc)
- Data from official sources (e.g. school records, census data, health data)
- Questionnaires or surveys
- Interviews or focus groups
- Observation of project activities or locations in the community (e.g. track graffiti, condition of playground, activity in public spaces, etc)
- Determine the frequency of the data collection and who will collect the information.
- Finally, determine how you will analyse your data and report your findings to funders, your community and your project partners and stakeholders.
See Appendix 2 - Sample evaluation plan for insights on how to create an evaluation plan.
Terminology
- Goal
- A goal is the long-term change in specific problems or situations that you want to see in your community.
- Objective
- Project objectives stem from the project goal(s) but are more specific and concrete. Objectives are then achieved through activities.
- Input
- Inputs identify the resources that are needed to make your project operate. They include things such as staff, facilities and equipment.
- Activity
- Activities are what the project will do to achieve the desired objectives.
- Output
- Outputs are the products, goods or services you expect to produce or deliver as part of your project, or the number of people you expect to serve. They represent the concrete results of your activities.
- Outcome
- Outcomes are the impacts or changes your project activities are expected to make in your community. Outcomes usually occur in stages. Some happen soon after the activities occur (immediate outcomes). These outcomes in turn lead to others down the road (intermediate and long-term outcomes). The long-term outcomes are usually the same as the overall goal(s), while the immediate and intermediate outcomes are similar to objectives. Sometimes several activities work together to achieve one outcome and sometimes one activity has several outcomes.
- Indicator
- An indicator is information that is collected about a particular process or outcome that lets you know whether it has occurred or not. It tells you what is observable and measurable. Ultimately, all the indicators together tell you whether your project was able to achieve its main objectives and if it went along as planned.
- Sources/Methods
- Information sources and data collection methodsare simply about where, how and when you will collect the information to document your indicators. Sources of information may include project staff, other agencies, participants and their families, members of the public and the media. Information may be collected via a variety of methods.
Appendix 1 - Sample project plan
Objective(s):
- Objective 1: To reduce the incidence(s) of dating violence among high school youth.
- Objective 2: To increase public awareness and understanding of dating violence as a serious issue.
Inputs What resources are needed to make your project operate? |
Activities What activities will take place during the project? |
Outputs How many and what kind of products/services will be generated from these activities? |
Outcomes What will happen as a result of your project? |
---|---|---|---|
Project coordinator Meeting space Transportation Library resources |
Phase 1 Problem assessment, consultation and development of crime prevention purpose (assessment phase) Organize meetings with key stakeholders (youth, parents, youth workers, school representatives, police, social workers, public health, etc.) to discuss dating violence as a current community problem. Get information on dating violence: books, articles, newspaper, statistics and reports. Identify risk factors (RF) and protective factors (PF) related to dating violence: gender (RF), low self-esteem (RF), negative attitudes about women/girls (RF), supportive adult role models (PF). |
Participation of key stakeholders/people who would like to help with the project Research activities completed Project plan developed |
Increased involvement of community stakeholders in collaborative efforts to reduce dating violence (immediate outcome) |
Volunteer staff Funding to cover design, printing costs |
Phase 2 Curriculum design Volunteer public health nurse and social worker will design curriculum that will include individual work, discussion groups, role modelling, skills training, a written information package and a community outreach component. A subcommittee of key stakeholders will review and approve curriculum content. |
Working sessions held to draft curriculum Curriculum that conforms to best practices in the literature, responds to community needs and is feasible given project resources Curriculum available and ready to use on time |
Increased availability of prevention resources relevant to the local community (immediate outcome) |
Project staff Meeting space |
Phase 3 Mentors deliver the curriculum (Implementation) Select and train mentors. Mentors will deliver the curriculum including individual activities to examine issues related to self-esteem; group exercises such as content analysis of film, music videos and other media to identify sex-role stereotypes communicated to youth; discussion about how youth receive these messages, what youth seek in intimate relationships and how they react when their needs are not met; and assertiveness, communication and conflict-resolution skills training to help youth clarify their needs and communicate them to others in clear and positive ways. |
Fifteen mentors are hired, trained Sessions are offered weekly to youth at the local youth centre Approximately 75 youth are reached |
Increased participant awareness about factors that contribute to teen dating violence (immediate outcome) Improved communication skills (intermediate outcome) Increased use of non-violent conflict resolution skills by participants (intermediate outcome) |
Rental facility Funding for information display, printing costs, audio-visual equipment. |
Phase 3 Public awareness activities (Implementation) Mentors work with participants to arrange interviews with local print and radio media to discuss what they've learned about the root causes of violence in dating relationships and to invite the community to a public awareness night. Participants put together an information booth and a public presentation based on the projects and ideas they worked on during the year in the mentoring sessions. |
Coverage in the local paper and on the local radio station Information booth and public presentation are held Information packages are produced and distributed Approximately 150 people attend the event |
Increased community awareness of the root causes of dating violence (immediate outcome) Improved community perceptions of the benefits of prevention activities to reduce dating violence (immediate outcome) |
Appendix 2 - Sample evaluation plan
Objective(s):
- Objective 1: To reduce the incidence of dating violence among high school youth.
- Objective 2: To increase public awareness and understanding of dating violence as a serious issue.
Outcomes What will happen as a result of your project? |
Indicators How will you know that the project is achieving its objectives and outcomes? |
Sources/methods What proposed source/method will be used to gather the information? |
||
---|---|---|---|---|
Source of Information | Tool/instrument used | Frequency of collection | ||
Phase 1 Increased involvement of community stakeholders in collaborative efforts to reduce dating violence |
Number of stakeholders who attend planning meetings Number of volunteer/in-kind hrs spent on collaborative efforts |
Project records | Minutes taken at meetings Time sheets maintained by stakeholders |
Monthly Ongoing record-keeping |
Enhanced commitment of key stakeholders to a comprehensive, evidence-based plan for addressing dating violence in the community | Number of stakeholders who have "signed on" to the project Extent to which plan reflects knowledge of "what works" to prevent dating violence among youth |
Letters of commitment Project Plan Literature |
Comparison of project plan to best practices identified in the literature | End of project |
Phase 2 Increased availability of prevention resources that conform to best practices in the literature and respond to community needs |
Extent to which curriculum reflects what is known about "what works" Extent to which curriculum is appropriate to the local context Extent to which curriculum is made available to the wider community |
Project Plan Literature Stakeholders Project records |
Comparison of project plan to best practices identified in the literature Key informant interviews with stakeholders and mentors | End of project End of project Ongoing record-keeping |
Phase 3 Increased participant awareness about factors that contribute to teen dating violence | Level of knowledge about factors leading to dating violence among youth | Participants | Test of participant awareness of the factors leading to dating violence | Before project sessions start and again when they are finished |
Improved communication skills | Level of communication skills among youth in project | Participants | Analysis of video-taped role play exercises | Start and end of project |
Increased participant use of non-violent conflict resolution | Level of conflict resolution skills among youth in project | Participants | Video-taped role play exercises | Start and end of project |
Percentage of information night attendees who report they are more aware of the root causes of dating violence after the evening than they were before | Attendees at information night | One-page survey of a random sample of people attending the public awareness night | End of the event | |
Percentage of information night attendees who report they are have more positive perceptions of the benefits of prevention activities after the evening than before | Attendees at information night | One-page survey of a random sample of people attending the public awareness night | End of the event |
Crime Prevention News Releases
-
Government of Canada helps religious organizations in Windsor protect themselves against hate-motivated crimes
November 15, 2024 -
Minister LeBlanc launches Call for Applications under National Crime Prevention Strategy
October 25, 2024 -
Government of Canada National Action Plan results in 19 per cent decline in auto theft
October 16, 2024 - More Crime Prevention News Releases
Crime Prevention Publications and Reports
- 2023 Annual National Data Report to Inform Trends and Patterns in Drug-Impaired Driving
- Anniversary of the Release of the Mass Casualty Commission Final Report
- Crime Prevention in Indigenous Communities: An Examination of Culturally-Relevant Programs and Culturally-Competent Evaluation Approaches
- Methods of Preventing Corruption: A Review and Analysis of Select Approaches
- Research Summary - Methods of Preventing Corruption: A Review and Analysis of Select Approaches
- More Crime Prevention Publications and Reports
- Date modified: